Procedure
- Decision to initiate: 04.09.2008
- Resolution on approval and display: 10.09.2008
- Resolution on statute: 25.05.2009
- Legal force through public announcement: 14.01.2010
Plan content
The planning objectives were:
- Designation as an area for public use
- Construction of a new three-storey building adjacent to the existing building of the Eastside Youth Club (formerly the Post Kindergarten).
- Supplementing the use of the site with the function of a single-form entry primary and regular school in independent sponsorship (AWO).
- Redesign of the non-buildable property areas in the sense of painting 2
- Covering the parking space requirements caused by the project on the building plot itself.
Realisation status
The school is built and put into operation.