B-J 02 Galgenberg / western part (Jena-South)
Procedure
- Alignment plan, approval: 05.06.1939
- Transition decision: 12.06.1991
- Legal force through public announcement: 28.10.1991
Plan content
The aim of the development plan was to create additional building plots in Jena in order to meet the increasing demand at the time. The plan included the creation of a connecting road between Johann-Friedrich-Straße and Tatzendpromenade. The construction of two to three-storey residential buildings in open construction is permitted. In the northern part of the plan, the plan is replaced by the project-related development plan VBB-J 33 "Wohnen mit Weitblick - Friedensberg-Terrassen".
Realization status
Some of the planned roads and buildings have been implemented, but parts of the plan area are still undeveloped (as of July 2014).
Important note
The documents attached as downloads are for information purposes only. Only the legally binding copy of the plan that can be viewed at the urban planning department is authoritative.